U.S. Advanced Nuclear Deployment Tracker — Updated July 6, 2026

U.S. Advanced Nuclear Deployment Tracker

Updated July 6, 2026 · Selected U.S. advanced reactor projects based on publicly available information. See the legend at the end of the page.

Authority
Criticality
Company / Project Site Milestone progress Target / note Milestone reference
Completed / issued / approved
Under formal review / accepted for review
NRC pre-application engagement only — no application filed
In progress
Announced / planned
Not yet initiated
Not applicable as separate step
NRC pre-application
Early engagement with NRC before a formal licensing application. It does not mean NRC approval.
NRC SDA
Standard Design Approval — NRC design approval. It does not authorize construction or operation at any site.
NRC CP application / review
A construction permit application has been submitted, accepted, docketed, or is under NRC review. It is not a construction permit.
NRC CP issued
A construction permit has been issued. It authorizes construction, not fuel loading or operation.
NRC OL
Operating License — required before fuel loading and reactor operation under the Part 50 two-step path.
DOE NSDA
Nuclear Safety Design Agreement — DOE design-level safety milestone. It is not equivalent to an NRC SDA.
DOE PDSA
Preliminary Documented Safety Analysis — DOE project/site safety step. It is not equivalent to an NRC CP.
DOE DSA / readiness
DOE final documented safety and readiness sequence before criticality or operation. It is not equivalent to an NRC OL.
DOD pathway
Department of Defense demonstration or acquisition authority. It is separate from NRC and DOE civilian pathways.
Important: This tracker compares milestones across different authorization systems, but those systems are not legally equivalent. A green dot under NRC "Design approval" means NRC SDA only when an SDA exists. A green dot under DOE "Design approval" means a DOE design/safety milestone such as NSDA, PDSA, DSA, or equivalent depending on the project. A green dot under "Site auth." may mean NRC CP issued, DOE PDSA/DSA approved, or DOD project authorization depending on pathway. These are not interchangeable. Construction, fuel loading, criticality, and operation remain separate milestones. This tracker is a high-level strategic overview based on public information, not a regulatory determination.